Documents/SASCSR/5: Environment/5.3.2: Enhanced Commissioning/Indicator:1

Indicator: 1

[Outcome]

Measurements in/of Buildings Commissioned

Type Target Actual Actual Target
StartDate 2012-01-01 2012-01-01 2012-01-01 2013-01-01
EndDate 2012-12-31 2012-12-31 2012-12-31 2013-12-31
Number 2 1 2
Description Conduct enhanced commissioning for two owned buildings globally. SAS performed advanced, retrocommissioning on one of the primary office buildings at SAS headquarters and the data center in the UK. Commissioning ensures that building systems are operating efficiently and as intended so employees can do their jobs in a safe and comfortable environment and so SAS does not use more energy and water than necessary. A new office building in Sweden incorporated a ground-coupled geothermal heating system in 2012 and began installing solar on the rooftop set to be completed in 2014. Conduct enhanced commissioning for two owned buildings globally, including Sweden and UK data center expansion project.