Documents/DOIFACA2068/1: Recommandations/1: Make, Accept, Implement/Indicator:2

Indicator: 2

[Outcome]

Measurements in/of Recommendations Fully Accepted

Relationships:

Department of the Interior - Narrower_Than

Other Information:

Eastern Washington Resource Advisory Council

Type Target Actual
StartDate 2010-10-01 2010-10-01
EndDate 2011-09-30 2011-09-30
Percentage n/a 40
Description For a variety of its own reasons not applicable to the Committee, the agency may implement all/most of the recommendations, but few times recommendations are not implemented. RAC recommendations have great merit, but cannot always be implemented fully due to legal or policy constraints. Recommendations on the resource management plan were included in the analysis and some were incorporated for the next phase.